CMS is building three new schools in Huntersville, all funded by the 2023 $2.5B bond and all opening August 2028: Huntersville Elementary replacement, Middle School #2 North, and a North Meck High replacement.

Where Huntersville Elementary (Gilead Rd) · Middle School #2 North (13832 Stumptown Rd) · North Meck High (11201 Old Statesville Rd)
When All three open August 2028
Cost Funded by the 2023 $2.5B county bond

The three: (1) Huntersville Elementary replacement — a 45-classroom building costing slightly over $66 million, built behind the current Gilead Road school and facing Sherwood Drive, with contractor Swinerton. The old building stays in use until the new one is ready. (2) Middle School #2 North — a brand-new 54-classroom school for grades 6–8 on a 34-acre parcel at 13832 Stumptown Road, where land clearing is underway; it relieves Bailey, Bradley and J.M. Alexander middle schools. (3) North Mecklenburg High School replacement — a $134.1 million, three-story academic building at 11201 Old Statesville Road, about 19% complete as of August 2026, with structural steel going up and a new football field.

Separately, the CMS board approved $180 million in construction contracts on Nov. 11, 2026, for new schools at Beverly Woods, Huntersville and Berryhill. Details and renderings for all the bond projects are at cmsbondconstruction.com.

Source: Lake Norman Publications — CMS making progress on new north Mecklenburg schools (Oct 1, 2026); also Aug 12, 2026 Huntersville Elementary details and Aug 7, 2026 North Meck bond projects

✓ Verified Nov 14, 2026 — checked against the source linked above.