THE BRIDGE THAT COST DOUBLE — Huntersville Just Said Yes to a $10.4M Walkway

CharlotteNov 17, 2026

Huntersville just said yes to a bridge that costs twice what anybody planned — because the alternative is waiting years while the greenway stops at the highway.

The Town Board voted unanimously on Tuesday, Nov. 17, to accept the roughly $10.4 million bid for the pedestrian bridge that will carry the greenway over NC 73 at McDowell Creek, right by Birkdale Village. When the town first priced this thing out in 2023, it was about $5 million. The low bid came in at double that — and the board took it anyway.

Here is why it matters to anyone who walks, runs or bikes around here: right now the greenway dead-ends at NC 73. This bridge is the link — Huntersville to Cornelius to Davidson, one continuous path, no more darting across six lanes of traffic. It is the piece that turns three towns’ trails into one trail.

The money is mostly lined up, but not all of it. The town already paid a $2 million match in September and holds a roughly $3 million regional grant. The board asked the regional planning organization for another $1.3 million — an answer comes in the spring — and Mecklenburg County is working on about $1.5 million. If both come through, the town still needs roughly $2.5 million more.

The timing is not an accident. NC 73 widening construction starts early next year and runs four to five years — and the bridge goes up alongside it. Wait, and the price only climbs.

Guess the bridge is worth the walk — even at double the price.

Sources: Huntersville Today